MyFig Update
Posted By flanglois on June 22, 2018
11th St.
- Curbs and gutters have been poured and a section of new sidewalk has been poured next to Arashi and Testa between Hope and Flower – that section should open to pedestrians tomorrow morning.
- Work will be continuing this weekend from 7am-3pm Saturday and Sunday. This work will involve foundation work between Grand and Flower and lighting work between Broadway and Grand.
- Schedules are changing very often as the crews attempt to complete all work by early July, so I’m going to begin giving updates every couple days to make sure changes in schedule/progress get out to everyone.
- I also want to give a reminder that the final element of the 11th St. work will involve grinding down the existing road surface, laying new pavement and restriping for the entire length of 11th from Figueroa to Broadway. To get this over and done with as quickly as possible, they are going to take several days and do it all at once (likely closing several blocks at a time). No dates have been set yet and I will let everyone know as soon as they are, but please be aware that it will likely be sometime during the first 2 weeks of July.
Figueroa
- Bollards are being installed today and the new bike lane will be activated on Saturday morning.
For any of your employees, residents, patrons or vendors, please let them know how any of the above-mentioned work may impact them. Let me know if you have any questions and I’ll do my best to get you answers as soon as possible.
Please feel free to contact MyFIG directly:
Mat Talag, LADOT
(213) 305-0312
Josh Kreger
Director of Real Estate and Planning
South Park Business Improvement District
1100 S Flower St, Suite #3400, Los Angeles, CA 90015
josh@southpark.la | o. 213 663 1123 | c. 213-344-6749
southpark.la | Facebook | Twitter | Instagram
24/7 DISPATCH: 866-560-9346
24/7 DISPATCH: 866-560-9346
view commercial vacancies at: www.southpark.la/vacancies