MyFig Update
Posted By flanglois on June 7, 2018
MyFig 11th st work schedule through next week
Today and Tomorrow
Dig catch basin the within old roadway on east side of 11th and Hope.
This Weekend
Install electrical across 11th and Hill.
Mon. 6/11 – Tues. 6/12
Demo sidewalk between Hope and Flower including alley – access to alley will be closed from north side Mon-Fri. There will still be access from the south side with signs directing traffic.
Wed 6/13
Demo alley entrance Olive to Grand
Concrete pour Olive to Grand
Pour curb and gutter from Hope to Flower
Thurs. 6/14 – Fri 6/15
Demo sidewalk from Grand to Hope
Saturday 6/16
Re-open alley between Hope and Flower on Saturday morning
Pour curb and gutter Grand to Hope
During the above mentioned work, pedestrian access may be diverted during working hours to the north side of 11th. This is a safety precaution.
Also – once the sidewalk work is completed on 11th, they will repave the street. They are looking to repave the street all at once, perhaps with extended hours. There is no date for this work. I will let you know as soon as there is more information. Just wanted to give you an early reminder
For any of your employees, residents, patrons or vendors, please let them know how any of the above-mentioned work may impact them. Let me know if you have any questions and I’ll do my best to get you answers as soon as possible.
Please feel free to contact MyFIG directly:
Mat Talag, LADOT
(213) 305-0312
Josh Kreger
Director of Real Estate and Planning
South Park Business Improvement District
1100 S Flower St, Suite #3400, Los Angeles, CA 90015
josh@southpark.la | o. 213 663 1123 | c. 213-344-6749
southpark.la | Facebook | Twitter | Instagram
24/7 DISPATCH: 866-560-9346
24/7 DISPATCH: 866-560-9346
view commercial vacancies at: www.southpark.la/vacancies