MyFig Project Update
Posted By flanglois on May 22, 2018
11th St. WORK
5/22 – 5/27
Broadway to Grand: Street light and conduit work on the South side. MyFig construction team has been connected to Aven project team working on re-surfacing Margo Alley. I am working on getting details for how access to parking lot at SE corner of 11th and Olive will be provided. As soon as I get that information, I will share it with you.
During all above mentioned work, pedestrian access may be diverted during working hours to the north side of 11th. This is a safety precaution.
Figueroa Repaving
5/2 – 6/2
BSS has adjusted the Fig repaving schedule multiple times. Below is the latest schedule. It appears that there is no longer Fig repaving scheduled for 5/27, but I am still trying to get confirmation on that – I will share as soon as I have that info.
5/22-5/26
- Work type: repaving
- Location: 23rd St – Venice
- No full closure
- 2am-2pm
5/26
- work type: repaving
- location: Figueroa, between 8th – 11th
- scope: cold mill and paving
- no full closure
6/2
- work: slurry seal
- location: Figueroa, Venice – Pico
- full closure, 6A-6P
For any of your employees, residents, patrons or vendors, please let them know how any of the above-mentioned work may impact them. Let me know if you have any questions and I’ll do my best to get you answers as soon as possible.
Please feel free to contact MyFIG directly:
Mat Talag, LADOT
(213) 305-0312
Josh Kreger
Director of Real Estate and Planning
South Park Business Improvement District
1100 S Flower St, Suite #3400, Los Angeles, CA 90015
josh@southpark.la | o. 213 663 1123 | c. 213-344-6749
southpark.la | Facebook | Twitter | Instagram
24/7 DISPATCH: 866-560-9346
24/7 DISPATCH: 866-560-9346
view commercial vacancies at: www.southpark.la/vacancies