MyFig Update 1-8-18
Posted By flanglois on January 8, 2018
This week’s MyFIG work is expected to be lighter, compared to previous weeks. At this time full block closures are NOT anticipated this week.
1/8 – 1/9: MONDAY & TUESDAY
Due to the rain, work is limited for both days. Any work occurring will be within the construction zone and behind the k-rail.
1/10 – 12: WEDNESDAY – FRIDAY
LADWP will be working 1/10 and 1/11, from 9A to 3:30P, at 2 specific locations: Flower/11th and Olive/11th. All work will take place behind the k-rail.
All American, MyFIG’s general contractor, will be focusing on completing pouring the remaining concrete along the north side, primarily to complete the sidewalk ramps. This work will be completed from Broadway to Flower.
Aldridge, MyFIG’s electrical sub, will be focusing on completing electrical work for traffic signals. This work will occur primarily at the intersection of Olive/11th. Aldridge will also be working on completing any additional electrical work needed on other blocks along 11th. This work includes conduit installation and foundation, as well as pulling wiring.
For all work mentioned above, there is potential for traffic lanes to be limited on north/southbound streets. This is due to most of the work occurring at the corners of intersections. The limited lanes will not impact regular access to buildings.
Let me know if you have any questions and I’ll do my best to get you answers as soon as possible.
Please feel free to contact MyFIG directly:
Mat Talag, LADOT
(213) 305-0312
Katie Kiefer
Director of Operations
South Park Business Improvement District
1100 S. Flower St., Suite #3400, Los Angeles, CA 90015
katie@southpark.la | o. 213 663 1120
southpark.la | Facebook | Twitter | Instagram
24/7 DISPATCH: 866-560-9346