WINDOW WASH DELAY

There has been a significant delay in the window washing of the building. Each year the stage must be certified by a state licensed and CAL- OSHA approved vendor.
The process for certification has changed recently and is now quite extensive. The motor and braking system must be completely removed and taken to the shop of the vendor. There they take everything apart for evaluation and rebuild it as needed.
A complete electrical check is required along with an inspection of all cables, controls, leveling sensors, etc. The platform and the aluminum screen around the platform are thoroughly inspected as well.
This year the brakes were completely rebuilt, the 1000’ of steel cable was replaced and several areas of aluminum screen must be replaced.
The delay at this time is the aluminum screen has not arrived. We have been informed that it is held up in customs. This is a proprietary, patented high strength lightweight aluminum screen that is manufactured specifically for our type of Swingstage (washing equipment).
We apologize for this delay and will keep everyone informed when the cleaning of the windows and building is scheduled.

Location

1100 South Hope Street
Los Angeles, CA 90015
phone | (213) 742-0387

Management Team

General Manager
Francis Langlois, CCAM-HR | flanglois@actionlife.com

Manager Assistant
Taylor Jones | tjones@actionlife.com

Building Engineers
Steve Evans | sevans@actionlife.com

 

Management Company

Action Property Management
Regional Office
707 Wilshire Blvd., Suite 1475
Los Angeles, CA 90017
Office | 800-400-2284 EXT. 3608
(949) 450-0202

Corporate Office
2603 Main Street, Suite 500
Irvine, CA 92614
phone | (949) 450-0202
fax | (949) 450-0303